Wyoming-Jacksons Ferry 765 kV Project
Appalachian Power's 90-mile Wyoming-Jacksons Ferry 765-kilovolt (kV) transmission line connects power stations in Wyoming County, W.Va., and Jacksons Ferry, Va., and improves the reliability of service in the company’s West Virginia and Virginia service area. The area hasn’t seen major transmission reinforcement in more than 30 years

Why the line is needed
A new line is needed because customer demand for electricity is greater than the transmission system can supply. When the demands placed on the transmission system exceed its capability, there is an increased risk of system failure that could cause power outages and blackouts.

In 1973, the company completed the last major "backbone" 765 kV transmission line that serves the area. Since then, peak energy demand has more than doubled. In 1973, customers set a peak usage of 2,720 megawatts (MW). In 2004, customers' peak usage topped 7,000 MW.

Reasons for increased usage
The additional electricity demand results from growth in the number of customers, along with increased electricity usage by each customer. Per capita use of electricity is up due to more home appliances and other electric-powered conveniences and necessities. Although the area's population has remained relatively stable, increases have occurred in the number of households and businesses served as well as the number of customers who use electricity for efficient heating and cooling.

The solution, a new power line
Appalachian Power announced the power line project in March 1990. State regulators are charged with evaluating Appalachian's proposal and assessing alternatives. The Wyoming-Jacksons Ferry project was approved by state commissions in Virginia and West Virginia in May 2001 and March 2002, respectively. In addition, the project crosses federal land. In December 2002 the US Forest Service made a recommendation that the power line be allowed to cross 11 miles of federal land. Appalachian Power began clearing rights of way for the project in late 2003, and started construction in April 2004. The last of 333 towers was erected in October 2005. The line will be placed into operation in June, 2006.

How was the route selected?
Appalachian Power’s proposed power line routes were selected by experts from Virginia Tech and West Virginia University. They were charged with finding the most reasonable, least environmental impacting route available. Routing experts and the public provided input to the state commissions, who ultimately selected the approved route.